In project management, some of the most vulnerable points in a project occur where different teams meet and work passes from one team to another. These transitions, known as Give & Get points, are critical handover moments that can significantly affect the project schedule.
A Give Point is the point at which one team transfers a deliverable to another team. A Get Point is the corresponding point at which the receiving team expects to receive that deliverable and use it as an input for its next stage of work.
Every handover involves two teams and two commitments. The delivering team must complete and hand over its deliverable as planned, while the receiving team must be ready to take it over and continue the work.
When these commitments are not properly coordinated, problems can arise. A team may complete its work on time, but if the next team is not ready to take over, progress can stall. Similarly, a delay in delivering an input can prevent the receiving team from starting its work as planned. Either situation can create a ripple effect across the project.
This is why project managers need to identify and monitor these handovers well in advance. The Give & Get Report provides a structured way to manage these critical transitions. It brings inter-team dependencies into focus, helps identify potential bottlenecks, and enables the project manager to address coordination issues before they affect the project schedule.
Planning and Coordinating Give & Get Tasks
Give & Get control is introduced during the detailed planning stage. Every deliverable that requires a handoff between teams must be explicitly included in the work plan as two linked tasks: a Give task assigned to the team responsible for delivering the item, and a Get task assigned to the team responsible for receiving it.
The two teams must coordinate and agree on a handover date. This date should be based on when the receiving team needs the deliverable to proceed with its work. The delivering team should aim to complete the handover by that date or earlier, ensuring that the receiving team can start its work as planned.
The project manager must monitor both sides of the commitment: the delivering team’s progress toward completing the deliverable and the receiving team’s readiness to take it over. This helps prevent situations in which one team is waiting for the other, potentially delaying the project.
Breaking Down the Give & Get Report
The Give & Get Report provides an overview of all project handovers and their progress. It typically consists of six columns:
- Deliverable: The item being transferred from one team to another, such as a document, prototype, design, or research findings.
- Give Team: The team responsible for completing and delivering the deliverable.
- Planned Delivery Date: The date by which the Give Team plans to deliver the deliverable.
- Get Team: The team responsible for receiving the deliverable and continuing the work.
- Requested Delivery Date: The date by which the Get Team needs the deliverable to proceed with its work. Comparing this date with the planned delivery date helps identify scheduling gaps.
- Status: Indicates whether the handover is On Time, Ahead of Schedule, or Late.
The status is determined by comparing the planned delivery date with the requested delivery date:
- On Time: The planned delivery date is the same as or earlier than the requested delivery date.
- Late: The planned delivery date is later than the requested delivery date, meaning the receiving team will not get the deliverable when it needs it.
- Ahead of Schedule: The deliverable is actually handed over earlier than its planned delivery date.
Controlling the Relay Race
Project delays rarely appear without warning. Often, the first signs emerge at the points where one team depends on another to move forward.
The Give & Get Report makes these dependencies visible. It shows what needs to be delivered, who is responsible for delivering it, who is waiting to receive it, and when each handover must take place.
By reviewing these commitments and comparing planned delivery dates with the receiving teams’ requirements, project managers can:
- Identify potential bottlenecks before they affect the schedule.
- Detect conflicting expectations between teams.
- Follow up on deliverables that are at risk of being late.
- Ensure receiving teams have the resources and capacity to take over.
- Coordinate corrective actions before delays cascade into other project activities.
A successful handover requires both teams to fulfill their commitments. The Give & Get Report helps the project manager make sure both sides are ready, aligned, and accountable.